Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 77111 REL 7: 1995-057-02 EXP SOUTHERN IDAHO WILDLIFE MITIGATION
Project Number:
Title:
Shoshone-Bannock Wildlife Mitigation Projects
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Upper Snake Snake Upper 100.00%
Contract Number:
77111 REL 7
Contract Title:
1995-057-02 EXP SOUTHERN IDAHO WILDLIFE MITIGATION
Contract Continuation:
Previous: Next:
75040: 1995-057-02 EXP SOUTHERN IDAHO WILDLIFE MITIGATION
  • 77111 REL 17: 1995-057-02 EXP SOUTHERN IDAHO WILDLIFE MITIGATION
Contract Status:
Closed
Contract Description:
This contract is a continuation of the Shoshone-Bannock Tribes (SBT) SIWM program. Work under the FY18
contract will build on the work completed in FY17.

Highlights from the FY 17 SBT SIWM contract include:

1. Continued efforts on the acquisition of Lavaside North
2.  Participated in 2018 ISRP program review
3. Continued restoration efforts at Legacy Springs Mitigation area
a. Significant work in Russian olive removal using Tribal field crew
b. Weed control on grassland plantings
4. Continued restoration efforts at Bannock Creek Mitigation area
5. Continue Operations and Management on program lands

Highlights of work to be completed under the FY18 contract include:

1.  Close on Lavaside North property
2. Investigate potential land acquisitions
3. Continue habitat restoration efforts at the Legacy Springs Mitigation area.
a. Brush management to control Russian olive
b. plant grassland vegetation to control weeds and improve habitat based on test planting results
c. Weed control
d. shrub and riparian vegetation restoration project
4. Continue habitat restoration efforts at Bannock Creek
a. Russian olive removal
c. weed control
5. Continue operations and management on program lands.
Account Type(s):
Expense
Contract Start Date:
04/01/2018
Contract End Date:
03/31/2019
Current Contract Value:
$480,211
Expenditures:
$480,211

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Chad Colter Shoshone-Bannock Tribes Yes Supervisor chad.colter@sbtribes.com (208) 239-4553
Luca De Stefanis Bonneville Power Administration No Env. Compliance Lead ltdestefanis@bpa.gov (503) 230-5263
Aren Eddingsaas Shoshone-Bannock Tribes Yes Contract Manager aeddingsaas.sbtribes@gmail.com (208) 239-4577
Elsha Leavitt Shoshone-Bannock Tribes No Interested Party eleavitt@sbtribes.com (208) 478-3795
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
Shannell Ward Shoshone-Bannock Tribes No Administrative Contact shannell.ward@sbtribes.com (208) 478-3821
Pam Waterhouse Shoshone-Bannock Tribes No Administrative Contact pamela.waterhouse@sbtribes.com (208) 478-3819
Jacee Weed Shoshone-Bannock Tribes No Interested Party jacee.weed@sbtribes.com (208) 239-4551
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Ellen Wilt Bonneville Power Administration Yes COR ewwilt@bpa.gov (503) 230-5732
Elham Zolmajd-Haghighi Bonneville Power Administration Yes Contracting Officer ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration A: 119. Administration of BPA contracts 03/31/2019 03/31/2019
Receipt of EC documentation/clearance from BPA B: 165. Satisfy environmental compliance requirements 03/31/2019 03/31/2019
Coordinate project lands management with relevant land agencies C: 191. Coordinate project lands management with relevant land agencies 03/31/2019 03/31/2019
Identify potential mitigation properties D: 114. Identify potential mitigation properties 03/31/2019 03/31/2019
Conduct pre-acquisition activities E: 172. Conduct pre-acquisition activities 03/31/2019 03/31/2019
Develop and implement Legacy Springs riparian vegetation restoration efforts F: 47. Plant Vegetation- Legacy Springs riparian 03/31/2019
Develop and implement upland vegetation restoration efforts at Legacy Springs G: 47. Plant vegetation- Legacy Springs upland 12/01/2018 10/15/2018
Maintain vegetation on project lands- Bannock Creek H: 198. Maintain vegetation on project lands- Bannock Creek 12/01/2018 12/01/2018
Maintain vegetation on project lands- Legacy Springs I: 198. Maintain vegetation on project lands- Legacy Springs 12/01/2018 12/01/2018
Russian olive removal- Bannock Creek J: 199. Russian olive removal- Bannock Creek 03/31/2019 03/31/2019
Russian olive removal- Legacy Springs K: 199. Russian olive removal- Legacy Springs 01/31/2019 03/31/2019
Maintain program infrastructure L: 186. Maintain program infrastructure 03/31/2019 03/31/2019
Lease agricultural lands- Legacy Springs M: 194. Administer agricultural Lease- Legacy Springs 01/31/2019 03/31/2019
Lease agricultural lands- Lavaside N: 194. Administer agricultural Lease- Lavaside 03/31/2019 03/31/2019
Develop, install, and maintain public access information O: 188. Provide public access information 03/31/2019
Complete vegetation monitoring plan P: 174. Develop vegetation monitoring plan 03/31/2019
Complete management plan chapter for Cinder Cones property Q: 193. Produce management plan chapter for Cinder cone property 03/31/2019
Update Lavaside Management Plan Chapter to include Lavaside North Parcel R: 193. Update Lavaside management plan to include Lavaside North Acquisition 03/31/2019
Completed Annual Report fof FY2013-FY2017 S: 132. 5-year Progress Report for FY13-FY17 03/31/2019
Completed Annual Report FY2018 April 2018 to March 2019 T: 132. Submit Progress Report for the period (April 2018) to (March 2019 ) 03/31/2019

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 2 instances of WE 198 Maintain Vegetation
  • 2 instances of WE 199 Remove Vegetation
  • 2 instances of WE 193 Produce Land Management Plan
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Administration of BPA contracts 02/01/2018
B 165 Satisfy environmental compliance requirements 02/01/2018
C 191 Coordinate project lands management with relevant land agencies 02/01/2018
D 114 Identify potential mitigation properties 02/01/2018
E 172 Conduct pre-acquisition activities 02/01/2018
F 47 Plant Vegetation- Legacy Springs riparian 02/01/2018
G 47 Plant vegetation- Legacy Springs upland
H 198 Maintain vegetation on project lands- Bannock Creek 01/25/2018
I 198 Maintain vegetation on project lands- Legacy Springs 01/25/2018
J 199 Russian olive removal- Bannock Creek 02/01/2018
K 199 Russian olive removal- Legacy Springs 01/25/2018
L 186 Maintain program infrastructure
M 194 Administer agricultural Lease- Legacy Springs
N 194 Administer agricultural Lease- Lavaside
O 188 Provide public access information
P 174 Develop vegetation monitoring plan
Q 193 Produce management plan chapter for Cinder cone property
R 193 Update Lavaside management plan to include Lavaside North Acquisition
S 132 5-year Progress Report for FY13-FY17 02/01/2018
T 132 Submit Progress Report for the period (April 2018) to (March 2019 ) 02/01/2018
U 185 Periodic Status Reports for BPA 02/01/2018